Emergency Generator Canopy Systems
Army Corps. of Engineers, Big Cliff Dam, Oregon
Service Provided
- Design/Build new Emergency Generator Containment and canopy system to house the Emergency Generator for the Detroit and Big Cliff Dam facilities
- Provide and coordinate all design, engineering, excavation, crane, scaffolding, and inspection subcontractor's
- Excavate for and place new concrete foundations and containment walls
- Design/Fabricate new canopy systems
- Rig and placement of new generators within concrete containments
- Install new structural steel framework and associated siding, flashing, gutters, and downspouts
- Coordinate with other contractors and operating personnel to assure the least amount of plant interruption as possible. All work took place in close proximity to the only means of entry into the Detroit and Big Cliff Facilities during a period of multiple construction projects.
Project Statistics
- On schedule and under budget
- Trouble-free startup
Project Timeline
- Start date: December 2009
- Completion date: March 2010
Greenberry is a full service industrial mechanical contractor and fabricator serving clients throughout the U.S. and worldwide. Greenberry is stamped and certified by ASME, AISC certified for structural steel fabrication, and certified by the NQA-1 quality program for nuclear fabrication.